Release Engineering Memo [DRAFT]¶
Release Schedule Template¶
Milestone 1: Start of the Release (Date: ?)¶
- Matz appoints a release manager who will implement the schedule.
- Matz decides the "must-have" features.
- Matz approves the target date to release.
between 1 and 2¶
- This period focuses on determining feature requests.
- Some developer meetings should be held to determine requests.
Milestone 2: Feature Request Deadline (Date: about 3 mo. before)¶
- All new features must have been accepted.
- Otherwise, the feature will not be included in the next release.
between 2 and 3¶
- This period focuses on implementing the accepted features.
- It is also good to check bug tickets.
Milestone 3: Feature Implementation Deadline (Date: about 2 mo. before)¶
- All features must have been implemented.
- Otherwise, the feature will not be included in the next release.
- A preview release is made.
- Announcements to all developer mailing lists are made.
between 3 and 4¶
- This period focuses on fixing bugs.
- A developer meetings should be held to check all bug tickets.
Milestone 4: Code Freeze (Date: about 1 mo. before)¶
- The SVN trunk is copied to branches/
- All parts in trunk are free to modify.
- A rc release is made.
- Announcements to all mailing lists are made.
- Web site are updated.
between 4 and 5¶
- This period focuses on fixing only severe bugs.
- At least two developers must check a backport patch and agree on it.
- The (assistant) release managers only commit the branch.
Milestone 5: Final Release (Date: The day)¶
- The final release is made.
- Announcements to all mailing lists are made.
- Web site are updated.
- PARTY!!!